Construction Projects

Bidders looking for bid documents should visit the A/E Graphics Plan Room to view and acquire them: A/E Graphics Plan Room

photo 08-26-2014.jpg


Ten Year Road Improvement Plan

: Click Here


Other Projects:


2020 Road Program:
Road included for improvement in the 2020 Road Program:

CONTACT: Germantown DPW/Engineering, (262) 250-4721.
  1. Old Farm; Division Rd - Wagon Trail
  2. Harvest ln; Old Farm Rd - Thornapple Row
  3. Pheasant  Run; Old Farm Rd -  Thornapple Row
  4. Deer Crossing; Old Farm Rd-Thornapple Row
  5. Bridle Path; Old arm Rd -Thornapple Row
  6. Surrey Dr; Old Farm Rd - Thornapple Row
  7. Thornapple Row; Harvest ln - Surrey Dr.
  8.  Prairie Way; Surrey Dr - Wagon Trail
Basic Schedule (subject to change):

Sawcut curb; completed May 29, 2020 Remove curb; start Tuesday June 2, 2020

Replace curb; to start after catch basins and hydrants/valve replacement is complete est. 2-3 weeks to replace curb (est. 2-3 weeks after curb removal)

Milling of asphalt to begin after all catch basin, hydrant/valve replacement & curb is completed 2-3 days to perform milling operations (approx. start Mill July 13, 2020)

Estimated start Pavement is July 20, 2020 (approx. 3-4 days to place pavement)

Lovers Lane/Century Lane; Most likely an August start. Staff continues to design and acquire ROW for project.

Cromwell Drainage; estimated start in dryer part of summer, possibly July/August




WISCONSIN DOT PROJECTS



 INTERSTATE 41 UPGRADE:



CONTACT: Tammy Rabe, Project Manager, Wisconsin DOT, (920) 492-2212, Tammy.Rabe@dot.wi.gov