FOND DU LAC AVENUE PAVEMENT RESURFACING

WDOT contactors will begin pavement resurfacing on Fond du Lac Avenue (WIS 145) from Mequon Road to CTH P. Existing pavement will be repaired and resurfaced. Through traffic will be detoured beginning the week of July 17th. See schedule below

Week of July 10th
Mobilize traffic control and establish erosion control.

Week of July 17th
Establish Through Traffic Restrictions.  Road open to Local traffic only between Pilgrim Road and CTH P.  Local access maintained at all times.

Detour Through traffic using WIS 167 (Mequon Road) and IH 41.

Begin pavement removals, repair - CTH P to Mequon Road.

Begin sidewalk and curb repairs - Mequon Road to Park Ave., Village of Germantown

Week of July 24th
Close WIS 145 along Pilgrim Road at the Wisconsin Southern Railroad Crossing for 7 calendar days.

Local traffic detoured on WIS 167 (Mequon Road), Maple Road, County F (Freistadt Road), and Country Aire Drive.

Begin pavement resurfacing from CTH P to Mequon Road/

August
Complete pavement resurfacing and beam guard replacements.
Complete signing and pavement marking.
Restore through traffic

September
All work complete.
 
Fond du Lac Avenue Detour Map

Keith Martin
Project Leader
414-750-3085

Kurt Flierl, P.E.
Project Manager
414-750-3085

Adrian Lopez, P.E.
Supervisor
262-548-8755
Facebook Twitter Google Plus Email

Other News in Home

road construction.jpg

FIVE YEAR ROAD IMPROVEMENT PLAN

Posted on: April 19, 2017

STH-175 Reconstruction Project

Posted on: March 3, 2017
official-facebook-icon-png-4(2).png

Like us on Facebook!

Posted on: January 30, 2017