Construction Projects
Bidders looking for bid documents should visit the A/E Graphics Plan Room to view and acquire them:  A/E Graphics Plan Room

photo 08-26-2014.jpg

UPDATED MAY 24, 2016 (Recent updates in red text)

The following list presents the status of various projects going on in the Village:

2016 TID #6 WILLOW CREEK BUSINESS PARK (Appleton Ave.)

Grading & Erosion Control project:

The Grading & Erosion Control project will level off the site's surface creating future tenant building areas, storm water ponds, and an internal roadway.

BID RESULTS:
 Bid Value Bidder
$1,549,717.50 Super Western
$1,939,442.10 Veit
$2,321,515.25 Rams
$2,559,549.93 Michaels
$2,747,958.00 Edgerton

SCHEDULE:

03/01/2016:  Public Works & Highway Committee review of bids.
03/07/2016:  Village Board review of bids and contract award.

Spring 2016:  Project start-up.
07/15/2016:  Latest substantial completion date.
08/15/2016:  Final completion date.

CONTACT: Germantown DPW/Engineering, (262) 250-4720.


2016 PRIVATE PROPERTY INFILTRATION/INFLOW MITIGATION:

$300 thousand of improvements

This project will occur in the Glenwood Park and Hickory Hills neighborhoods.  Please view the work plan on the Germantown Wastewater Utility's PPI/I web page.
Work Plan

CONTACT: Germantown DPW/Engineering, (262) 250-4721.

WE ENERGIES' HIGH PRESSURE GAS MAIN RELAY PROJECT

WE Energies' contractors will begin this work this Winter ahead of the Village's Donges Bay Road reconstruction project.
Project Map

CONTACT:  WE Energies Project 24-Hour On-Call Representative, (877) 380-0522.

WISCONSIN DOT PROJECTS

1) APPLETON AVE (Maple Rd to Slinger Rd):

Year 2017

CONTACT: Aaron Palmer, Project Manager, Westbrook Associated Engineers, (608) 588-7866, or Douglas Cain, Project Manager, Wisconsin DOT, (262) 548-5603.

SCHEDULE:

-May 2016:  Plans, Specifications and Estimate



2) FOND DU LAC AVE. RESURFACING (Mequon Rd. to CTH P):

Year 2017

CONTACT: Douglas Cain, Project Manager, Wisconsin DOT, (262) 548-5603,

SCHEDULE:

-February 2016:  Early Plans, Specifications and Estimate.
-May 2016:  Plans, Specifications and Estimate
-September 2016:  Contract Let
-May 2017:  Project Start-up
-July 2017:  Project Completion


3) INTERSTATE 41 UPGRADE:

CONTACT: Tammy Rabe, Project Manager, Wisconsin DOT, (920) 492-2212,

4) MEQUON RD CORRIDOR STUDY (Wauwatosa Rd to Pilgrim Rd):

CONTACT: Paul Stankevich, Project Manager, Kapur & Associates, (414) 351-6668,  

5) MEQUON RD & COUNTRY AIRE DR INTERSECTION:

Year 2018

SCHEDULE:

-January 2016:  Final Storm Water Report
-February 2016:  Preliminary Plat; Final Environmental Report; Final Design Study Report
-April 2016:  Appraisal Plat
-August 2016:  1078 Utility Plans
-August 2017:  Draft Plans, Specifications & Estimate Submittal
-October 2017:  90%-completed Traffic Management Plan
-November 2017:  Final Plans, Specifications & Estimate
-April 2018:  Contract Let
-2018:  Construction

CONTACT: Andy Smieja, DAAR Engineering, (414) 225-9817,

Contact Us
John Laning
Village Engineer
Email

Engineering Department
N112 W17001 Mequon Road
Germantown, WI 53022-0337

Ph: 262-250-4720
Fx: 262-253-8255

Hours
Monday - Friday
8 a.m. - 4:30 p.m.

Staff Directory